Architect's rendering
43,408-square-foot building
To be located on Acadia Street (vacant lot)
Total Project Budget: $6,976,450
Design Team:
Architect – ADW Architects of Charlotte
Civil – Timmons Group
Structural – Stewart Engineering
Mechanical, Electrical, Plumbing + Fire Protection – Stanford White
Audio/Visual/Security – VuePoint Consulting
Schedule:
Early Site Activities:
Site Tree Removal and Clearing
Contractor - Lusk Tree Service
Construction Start May 2012
Construction Finish June 2012
Temporary Construction Fence
Contractor - Fence Builders
Construction Start May 2012
Construction Finish June 2012
Demolition of 2008 Sunnyside Avenue Residence
Reclamation of Important Architectural Items from 2008 Sunnyside
Contractor – Triad Builders of King
Construction Start May 2012
Construction Finish May 2012
Asbestos Abatement
Contractor – Clean Air Environmental
Abatement Start June 2012
Abatement Finish June 2012
Demolition of Building
Contractor – Bodford Construction
Construction Start June 2012
Construction Finish June 2012
Building Construction
Contractor Bidding October 2012
Construction Start November 2012 (estimated)
Construction Finish December 2013 (estimated)
|