Architect's rendering
Film Production Design Building
(set design and construction, animation, and gaming) |
29,993-square-foot building
To be located near the Waughtown Street entrance to campus
Total Project Budget: $11,543,828
Design Team:
Architect – BBH Design of Raleigh
Associate Architect – Deborah Berke & Partners Architects of New York City
Civil/Structural – Mulkey Engineers & Consultants
Mechanical, Electrical, Plumbing + Fire Protection – RMF Engineering
Landscape – Lappas + Havener
Interior Design – Interior Architecture & Design
Schedule:
Early Site Activities
Temporary Construction Fence
Contractor - Fence Builders
Construction Start June 2012
Construction Finish June 2012
Demolition of 172 and 178 Waughtown Street Buildings
Asbestos Abatement
Contractor – Clean Air Environmental
Abatement Start June 2012
Abatement Finish June 2012
Building Demolition
Contractor – The Outdoorsman
Construction Start June 2012
Construction Finish June 2012
Building Construction (In Final Design Stage)
Contractor Bidding October 2012
Construction Start November 2012 (estimated)
Construction Finish December 2013 (estimated)
|