Architect's rendering
9,023-square-foot building
To be located on campus adjacent to the current location (off Kenan Drive)
Total Project Budget: $3,260,666
Design Team:
Architect – ADW Architects
Civil – Timmons Group
Structural – Stewart Engineering
Mechanical, Electrical, Plumbing + Fire Protection – Stanford White
Audio/Visual/Security – VuePoint Consulting
Schedule:
Early Site Activities
Site Tree Removal and Clearing
Contractor - Lusk Tree Service
Construction Start May 2012
Construction Finish June 2012
Temporary Construction Fence
Contractor - Fence Builders
Construction Start May 2012
Construction Finish May 2012
Site Demolition of Asphalt and Concrete Surfaces
Contractor - The Outdoorsman
Construction Start June 2012
Construction Finish June 2012
Accessible Path to Center Stage
Contractor - Fletcher Brothers Concrete
Construction Start June 2012
Construction Finish June 2012
Building Construction
Contractor Bidding October 2012
Construction Start November 2012 (estimated)
Construction Finish November 2013 (estimated)
|