Architect's rendering

 

Library

75,731-square-foot building

To be located across from the Administration Building on Ehle Drive 

Total Project Budget: $24,009,268

Design Team:    

Architect – Pearce Brinkley Cease + Lee of Raleigh

Library Consultant – Design Lab Architects of Boston

Civil – Allied Design

Structural – LHC Structural Engineers

Mechanical, Electrical, Plumbing + Fire Protection – Stanford White

Landscape – Lappas + Havener

Audio/Visual – Thornburn Associates

Interior Design – Perkins + Will

 

Schedule:

Early Site Package

Contractor – BECO Inc.

Construction Start           May 2012

Construction Finish         August 2012

Building Construction

Contractor                          Bidding October 2012

Construction Start           November 2012 (estimated)

Construction Finish        January 2014 (estimated)

 

Associated Projects:                               

Ehle Street and Parking Lighting

Contractor – BECO Inc.

Construction Start           February 2012

Construction Finish        August 2012

Duke Energy Utility Relocation

Contractor – Duke Energy (Pike Electric)

Construction Start           April 2012

Construction Finish        November 2012 (estimated to remove poles)

AT&T , Time Warner Cable, City of Winston-Salem, N.C. Department of Transportation Utility Relocation/Signal Cable

Contractor – AT&T, Time Warner, City of WS, NC DOT

Construction Start           May 2012

Construction Finish        October 2012 (estimated)

Pedestrian Accessible Path/Walks

Contractor – Alan Barber Concrete

Construction Start           April 2012

Construction Finish        April 2012

Temporary Construction Fence

Contractor – Fence Builders

Construction Start           April 2012

Construction Finish         May 2012